New Elementary School on Park Road

SCOPE OF WORK
Replace with 45-classroom school for Dilworth paired schools.

PROGRESS
Site work is continuing at the New Elementary School on Park Road with mass grading and installation of underground utilities. Both modulars are being removed from the site which allows site work to continue. Demolition of the old school is complete. The project consists of a new 45-classroom elementary school. Completion is scheduled for August of 2026.

UPDATED
February 2025
Construction Manager /
General Contractor
Vannoy-McFarland, a JV
Architect
Ratio
Location
3701 Haven Drive Charlotte, NC 28209
Project Manager
Ryan Thornburg
Construction Percent Complete
9%
Occupy On
August 2026
Board District
District 5