New Elementary School on Park Road

SCOPE OF WORK
Replace with 45-classroom school for Dilworth paired schools.

PROGRESS
The New Elementary School on Park Road project started this month with the issuance of notice to proceed for the demolition of the old school and site work for the new school. Installation of construction fencing and preparations for the demolition of the school building continues. The project has completed the construction documents review phase and submitted for permit. The construction manager will bid the remaining scope packages in December. The project consists of a new 45-classroom elementary school.

UPDATED
October 2024
Construction Manager /
General Contractor
Vannoy-McFarland, a JV
Architect
Ratio
Location
3701 Haven Drive Charlotte, NC 28209
Project Manager
Ken Brown
Construction Percent Complete
1%
Occupy On
August 2026
Board District
District 5