New Elementary School on Park Road

SCOPE OF WORK
Replace with 45-classroom school for Dilworth paired schools.

PROGRESS
New Elementary School on Park Road is continuing with building foundations and finish grading of the building pad. The plumber, electrician and mason will mobilize in May.

UPDATED
April 2025
Construction Manager /
General Contractor
Vannoy-McFarland, a JV
Architect
Ratio
Location
3701 Haven Drive Charlotte, NC 28209
Project Manager
Ryan Thornburg
Construction Percent Complete
15%
Occupy On
August 2026
Board District
District 5