SCOPE OF WORK
Baseline 54-classroom Middle School facility to relieve Community House MS, Jay M. Robinson MS and Rea Farms STEAM K-8.

PROGRESS
The team has coordinated the traffic signal installation at the Tom Short entrance. The team is also working through the remaining punch list items and finalizing the building systems closeout.

UPDATED
October 2026
Construction Manager /
General Contractor
Messer Construction Company
Architect
Hord Coplan Macht, Inc.
Location
5410 Camp Verde Lane Charlotte, NC 28277
Project Manager
Ryan Thornburg
Construction Percent Complete
99%
Occupy On
August 2026
Board District
District 6

CURRENT PROJECT PHOTOS