North Mecklenburg HS

SCOPE OF WORK
Onsite replacement of balance of campus and comprehensive athletics package.

PROGRESS
The North Mecklenburg High School Replacement project has completed the design development phase; the architect is currently reviewing and incorporating comments into the project's design. The project update meeting was conducted at the school; interested parents, students and staff attended. As the design progresses, the construction manager continues to update logistics plans required to safely execute and coordinate the complex construction project. The project provides a full replacement of the comprehensive high school.

UPDATED
October 2024
Construction Manager /
General Contractor
New Atlantic Contracting, Inc.
Architect
ADW Architects
Location
Old Statesville Road Huntersville, NC 28078
Project Manager
Kenneth Brown
Construction Percent Complete
0%
Occupy On
August 2028
Board District
District 1