West Mecklenburg High School

SCOPE OF WORK
Renovate/replace gymnasium built in 1954.

PROGRESS
The West Mecklenburg High School Gym Replacement (17) construction manager has the building pad for the new gym on grade. This will allow the under slab rough-in to begin and foundation footings are progressing. The existing site utilities have been relocated to allow construction to progress. The site contractor continues to install underground storm water piping. The stadium access drive has now been paved and opened for use. The construction lay down area is fenced and isolated from the student/staff parking lot.

UPDATED
September 2020
Construction Manager /
General Contractor
Barnhill/D.A. Everett
Architect
Moseley Architects
Location
7400 Tuckaseegee Road Charlotte, NC 28214
Overall Budget
$10,850,902
Project Manager
Chip Lofton
Construction Percent Complete
7%
Occupy On
August 2021
Board District
District 2

CURRENT PROJECT PHOTOS



PREVIOUS CONSTRUCTION PHOTOS