SCOPE OF WORK
Provide new gymnasium, the existing gymnasium will become the auxilliary.

PROGRESS
The West Mecklenburg High School Gym construction manager has the building completely dried and the MEP trades are finalizing rough-ins. The bathroom floor/wall tile is progressing and the painter is installing final finishes. Roof top units have been set and energized and conditioned air is running, the gym wood floor will follow. The site contractor is pouring sidewalks and maintaining erosion control.

UPDATED
April 2021
Construction Manager /
General Contractor
Barnhill/D.A. Everett (CM)
Architect
Moseley Architects
Location
7400 Tuckaseegee Road Charlotte, NC 28214
Overall Budget
$10,850,902
Project Manager
Chip Lofton
Construction Percent Complete
68%
Occupy On
August 2021
Board District
District 2