West Charlotte High School

SCOPE OF WORK
New 100 classroom school to replace current facility built in 1954.

PROGRESS
The West Charlotte High School construction manager has now completed the building structure. The load bearing masonry walls and steel erection is complete and floor slabs have been poured. The MEP contractors are working on building rough-ins throughout the facility. The roofing contractor continues to install the roofing membrane now that roof deck is completed. The brick veneer is progressing around the exterior elevations. The athletic buildings around the stadium have moved into interior MEP rough-ins. The site contractor has started construction of the north parking lot.

UPDATED
April 2021
Construction Manager /
General Contractor
Rodgers/Holt Brothers (CM)
Architect
LS3P
Location
2219 Senior Drive Charlotte, NC 28216
Overall Budget
$109,977,166
Project Manager
Chip Lofton
Construction Percent Complete
43%
Occupy On
August 2022
Board District
District 2

CURRENT PROJECT PHOTOS


LIVE CAMERA

Click here to open Live Cameraenter image description here in new tab.

PREVIOUS CONSTRUCTION PHOTOS