West Charlotte High School

SCOPE OF WORK
New 100 classroom school to replace current facility built in 1954.

PROGRESS
The West Charlotte High School (17) construction manager has completed selective demolition including athletic field houses, stadium concessions and football field site light poles. The erosion control ponds were completed allowing the next phase of site grading to progress. Site utilities were able to progress and underground piping is being installed for water, sewer and fire lines. The building pad was brought to grade and the building footings were started. A virtual project information update meeting will be held on July 16.

UPDATED
June 2020
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
LS3P
Location
2219 Senior Drive Charlotte, NC 28216
Overall Budget
$109,977,166
Project Manager
Chip Lofton
Occupy On
August 2022
Board District
District 2