West Charlotte High School

SCOPE OF WORK
New 100 classroom school to replace current facility built in 1954.

PROGRESS
The West Charlotte High School (17) construction manager is continuing the work throughout the new facility. The prep for slab on grade continues on the north end of the new building. This prep mainly requires underground electric and plumbing. The south end now has load bearing masonry progressing. They have started prep for the pool and continue with waterproofing. The site contractor is installing below grade storm water piping and structures. The existing campus storm water piping has been tied into the new structures.

UPDATED
September 2020
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
LS3P
Location
2219 Senior Drive Charlotte, NC 28216
Overall Budget
$109,977,166
Project Manager
Chip Lofton
Construction Percent Complete
10%
Occupy On
August 2022
Board District
District 2

CURRENT PROJECT PHOTOS


LIVE CAMERA

Click here to open Live Cameraenter image description here in new tab.