New 100 classroom school to replace current facility built in 1954.
PROGRESS
The trade contractors continue to work throughout the West Charlotte High School facility. Finishes throughout the facility are progressing well. The final clean operation has started at most areas in preparation for owner/architect punch list. Finishes are still being completed at the auditorium and pool area. The gym acoustical treatments and athletic accent striping are also installed. Kitchen equipment for culinary arts and child nutrition is being delivered and installed. The site contractor continues hardscapes around the building and sod install is starting soon. The team is now working with administration to finalize transition plans from Phase 1 to Phase 2. The stadium improvements including the field house and concession stands are nearing completion. The new bus lot will have the finish coat of asphalt installed in early May.