South Mecklenburg HS

SCOPE OF WORK
Replace classroom building built in 1958 to upgrade learning conditions.

PROGRESS
The South Mecklenburg High School construction manager has been working on brick veneer at all the exterior elevations. This has also allowed window installations to begin. The dry wall installation is nearing completion. The painter has started prime paint on the first floor. Mechanical, electrical and plumbing trades are finishing over-head rough ins which will allow finishes to progress.

UPDATED
June 2024
Construction Manager /
General Contractor
Balfour Beatty
Architect
Morris Berg
Location
8900 Park Road Charlotte, NC 28210
Overall Budget
$17,322,927
Project Manager
Chip Lofton
Construction Percent Complete
60%
Occupy On
January 2025
Board District
District 5