South Academy of International Languages (fka New K-8 School (South)

SCOPE OF WORK
New K-8 Language Immersion facility located on the old Nations Ford Elementary School site.

PROGRESS
The construction manager for the South Academy of International Languages (FNA New K-8 Language Immersion South (17) is working diligently throughout the building with multiple trades on site. The installation of finish paint, ceiling grid, casework and flooring installations are ongoing throughout the building. Trim-out of the MEP (mechanical, electrical and plumbing) are continuing and the permanent HVAC system is up and running. Sidewalks, final paving and canopies were installed.

UPDATED
January 2021
Construction Manager /
General Contractor
Messer Construction (CM)
Architect
FWA
Location
8300 Nations Ford Road Charlotte, NC 28217
Overall Budget
$42,959,367
Project Manager
Ken Brown
Construction Percent Complete
91%
Occupy On
August 2021
Board District
District 2