Shamrock Gardens Elementary School

SCOPE OF WORK
New 45-classroom replacement facility.

PROGRESS
The Shamrock Gardens Elementary School construction manager mobilized multiple trades on the project during the month. The steel contractor completed the installation of the structural steel, bar joist and decking. The mason continued with brick installation throughout the exterior of the building and completed the interior CMU. Exterior studs continued on the classroom wing and interior metal studs began in the administration and first floor classroom wing. The installation of the wall insulation progressed in the available areas. The MEP trades continued throughout the building with above ceiling and in wall rough-ins. The landscaper mobilized to install areas that were available to take advantage of the fall planting season.

UPDATED
September 2021
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
Little Diversified Architectural
Location
3301 Country Club Drive Charlotte, NC 28205
Overall Budget
$32,358,351
Project Manager
Ken Brown
Construction Percent Complete
46%
Occupy On
August 2022
Board District
District 4

CURRENT PROJECT PHOTOS



Live Camera
 .

Click here to open Live Cameraenter image description here in new tab.

Click Here for 09.17.2020 Project Information Meeting

PREVIOUS CONSTRUCTION PHOTOS