Shamrock Gardens ES

SCOPE OF WORK
New 45-classroom replacement facility.

PROGRESS
Project is complete.

UPDATED
March 2024
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
Little Diversified Architectural
Location
3301 Country Club Drive Charlotte, NC 28205
Overall Budget
$30,084,692
Project Manager
Ken Brown
Construction Percent Complete
100%
Occupy On
August 2022
Board District
District 4

CURRENT PROJECT PHOTOS



 .