Shamrock Gardens Elementary School

SCOPE OF WORK
New 45-classroom replacement facility.

PROGRESS
The Shamrock Gardens Elementary School construction manager continued to push the project to completion. Final clean continued in the administration, media center, music and arts spaces in allowing the architect to begin review of the spaces for punch list. Striping of the bus and staff parking lots was completed and the conversion of the temporary detention basin to permanent started.

UPDATED
April 2022
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
Little Diversified Architectural
Location
3301 Country Club Drive Charlotte, NC 28205
Overall Budget
$31,358,351
Project Manager
Ken Brown
Construction Percent Complete
98%
Occupy On
August 2022
Board District
District 4

CURRENT PROJECT PHOTOS



Live Camera
 .

Click here to open Live Cameraenter image description here in new tab.

Click Here for 09.17.2020 Project Information Meeting

PREVIOUS CONSTRUCTION PHOTOS