Shamrock Gardens Elementary School

SCOPE OF WORK
New 45-classroom replacement facility.

PROGRESS
The Shamrock Gardens Elementary School has been occupied by staff and students. The construction manager continues completing punch list items and final closeout documents.

UPDATED
August 2022
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
Little Diversified Architectural
Location
3301 Country Club Drive Charlotte, NC 28205
Overall Budget
$31,358,351
Project Manager
Ken Brown
Construction Percent Complete
99%
Occupy On
August 2022
Board District
District 4