PROGRESS
The Shamrock Gardens Elementary School construction manager completed the aggregate piers and lime stabilization. The footings have started in the kitchen/cafeteria and the electrician and plumber have mobilized to begin below slab rough-ins. Installation of erosion control measures continued and grading of the staff parking lot started.

UPDATED
April 2021
Construction Manager /
General Contractor
Rodgers/Holt Brothers
Architect
Little Diversified Architectural
Location
3301 Country Club Drive Charlotte, NC 28205
Overall Budget
$35,358,351
Project Manager
Ken Brown
Construction Percent Complete
8%
Occupy On
August 2022
Board District
District 4