New High School (Olympic Relief)

SCOPE OF WORK
New 100 classroom high school; relieves crowding at Olympic High School.

PROGRESS
The construction manager for the New High School Olympic Relief (17) continued with fine grading and utility installation operations throughout the site. The mason continued with below grade masonry in preparation of concrete slabs and installed the vertical load bearing CMU. The pool contractor began installation of the surge tank and underground utilities. Structural steel installations began in the building 4 classroom wing and the cafeteria/kitchen. Underground plumbing and electrical continued in the areas that come available. The 100-classroom relief high school is scheduled to be occupied in August 2022.

UPDATED
September 2020
Construction Manager /
General Contractor
Edifice
Architect
Little Diversified Architectural
Location
14947 York Road Charlotte, NC 28278
Overall Budget
$109,908,793
Project Manager
Ken Brown
Construction Percent Complete
18%
Occupy On
August 2022
Board District
District 2

CURRENT PROJECT PHOTOS


LIVE CAMERA

Click here to open Live Cameraenter image description here in new tab.

PREVIOUS CONSTRUCTION PHOTOS