Northwest School of the Arts

SCOPE OF WORK
Replace classroom buildings B&D and build classroom addition that supports program. 1st phase includes parking and U/G stormwater.

PROGRESS
The Northwest School of the Arts construction manager continued on Phase 1 installing the underground detention system and began final grading the site. The electrician mobilized and installed underground conduit for the new light poles. Preparations began for the new domestic water, fire line and sewer connections. The Phase 1 scope includes underground storm water detention system and new car parking lot in preparation for the new building in Phase 2.

UPDATED
October 2023
Construction Manager /
General Contractor
Balfour Beatty
Architect
LS3P
Location
1415 Beatties Ford Road Charlotte, NC 28216
Overall Budget
$12,167,000
Project Manager
Ken Brown
Construction Percent Complete
38%
Occupy On
January 2025
Board District
District 2

CURRENT PROJECT PHOTOS



PREVIOUS CONSTRUCTION PHOTOS