Replace classroom buildings B&D and build classroom addition that supports program. 1st phase includes parking and U/G stormwater.
PROGRESS
The Northwest School of the Arts construction manager continued on Phase 1 installing the underground detention system and began final grading the site. The electrician mobilized and installed underground conduit for the new light poles. Preparations began for the new domestic water, fire line and sewer connections. The Phase 1 scope includes underground storm water detention system and new car parking lot in preparation for the new building in Phase 2.