North Mecklenburg High School

SCOPE OF WORK
On-site replacement of balance of campus and comprehensive athletics package.

PROGRESS
Construction continues to make good progress. Current work includes installing the press box at the football stadium, completing the track surface, and installing utilities in the support buildings. Structural steel installation is also progressing well in the main school building. The project team remains engaged with school administration to provide updates, address questions, and support the successful delivery of the project.

UPDATED
July 2026
Construction Manager /
General Contractor
New Atlantic Contracting, Inc.
Architect
ADW Architects
Location
Old Statesville Road Huntersville, NC 28078
Project Manager
Ryan Thornburg
Construction Percent Complete
19%
Occupy On
August 2028
Board District
District 1

CURRENT PROJECT PHOTOS



LIVE CAMERA