New K-8 School (South)

SCOPE OF WORK
New K-8 Language Immersion facility located on the old Nations Ford Elementary School site.

PROGRESS
The construction manager for the New K-8 Language Immersion South (17) continued with tile installations throughout the building. Paint continued in the gym and media center. The classroom window systems are 98% complete and are waiting for the delivery of the storefront door systems. The mechanical, electrical and plumbing contractors worked throughout the entire building with above ceiling and in-wall installations. Metal stud installation is 75% complete on the second floor of the classroom wing. The team is working to bring the mechanical units online in areas ready mid-October.

UPDATED
September 2020
Construction Manager /
General Contractor
Messer Construction (CM)
Architect
FWA
Location
8300 Nations Ford Road Charlotte, NC 28217
Overall Budget
$42,959,367
Project Manager
Kenneth Brown
Construction Percent Complete
69%
Occupy On
August 2021
Board District
District 2