Ballantyne Ridge High School

SCOPE OF WORK
New 100 classroom high school to relieve South Mecklenburg, Ardrey Kell and Myers Park HS.

PROGRESS
The new Ballantyne Ridge High School project team continued coordinating the numerous trades on site. The mason continued with interior CMU and brick veneer installation throughout the building. Spray fireproofing continued on the fourth floor of the clas

UPDATED
February 2024
Construction Manager /
General Contractor
Messer
Architect
Ratio
Location
4004 Toringdon Way Charlotte, NC 28277
Overall Budget
$148,962,116
Project Manager
Kenneth Brown
Construction Percent Complete
82%
Occupy On
August 2024
Board District