Ballantyne Ridge High School

SCOPE OF WORK
New 100 classroom high school to relieve South Mecklenburg, Ardrey Kell and Myers Park HS.

PROGRESS
The New Ballantyne Ridge High School (fka New High School (South, Ardrey Relief) construction manager continued coordinating the numerous trades on site. The mason continued with interior CMU and brick veneer installation throughout the building. Spray fi

UPDATED
January 2024
Construction Manager /
General Contractor
Messer
Architect
Ratio
Location
4004 Toringdon Way Charlotte, NC 28277
Overall Budget
$148,962,116
Project Manager
Kenneth Brown
Construction Percent Complete
79%
Occupy On
August 2024
Board District