New Elementary School (Windsor, Winterfield, Idlewild Road)

SCOPE OF WORK
New 45-classroom elementary school to relieve Windsor, Winterfield, and Idlewild ES.

PROGRESS
The New Elementary School (Windsor Park, Winterfield, Idlewild Relief) construction manager continues site grading. A section of the classroom building is on grade allowing some footings to progress. There are Duke Power underground primary lines feeding the adjacent property owners that will need to be relocated requiring executed easements. Getting these documents finalized and the lines relocated is holding up the completion of the remaining site work and potentially impacting the construction completion date. The site contractor has been able to set the stone for the new bus lot including the curb and gutter. The site contractor continues to monitor and maintain the perimeter erosion control.

UPDATED
August 2022
Construction Manager /
General Contractor
Rogers / Holt Bros. III
Architect
Neighboring Concepts
Location
5932 Farm Pond Lane Charlotte, NC 28212
Overall Budget
$45,297,022
Project Manager
Mike Higgins
Construction Percent Complete
6%
Occupy On
August 2023
Board District
District 4