New Elementary School (Nations, Sterling, Steele Creek Relief)

SCOPE OF WORK
New 45-classroom elementary school to relieve Nations Ford, Sterling, and Steele Creek.

PROGRESS
The New Elementary School (Nations, Sterling, Steele Creek Relief) (17) construction manager continued with the installation of site utilities throughout the site. The building footings were completed allowing the below grade CMU, under slab plumbing and electrical to be installed in the classroom and administration wings. Structural steel operations began in the administration wing. The new 45-classroom relief elementary school is scheduled to be occupied August of 2021.

UPDATED
September 2020
Construction Manager /
General Contractor
Metcon (CM)
Architect
FWA
Location
2541 Sandy Porter Road Charlotte, NC 28273
Overall Budget
$31,572,550
Project Manager
Ken Brown
Construction Percent Complete
19%
Occupy On
August 2021
Board District
District 2