New Elementary School (Elon, Hawk Ridge, Polo Relief)
SCOPE OF WORK
New 45-classroom elementary school to relieve Elon, Hawk Ridge, Polo.
PROGRESS
The New Elementary School (Elon, Hawk Ridge, Polo Relief) construction manager completed the building footings, underground electrical and plumbing rough-ins. The mason continued with load bearing masonry walls in areas B and A. The recreation center footings were installed and below grade masonry continued. The project team is working to identify options to mitigate schedule impacts from the later and anticipated receipt of permits, masonry delays and potential supply chain issues. The road procurement package has been revised and will rebid in early 2023.