New Elementary School (Bain, Lebanon, Piney Grove)

SCOPE OF WORK
New 45-classroom elementary school; relieves crowding at Bain, Lebanon Road, Piney Grove.

PROGRESS
The New Elementary School (Bain, Lebanon, Piney Grove Relief) continued prepping and pouring the slab on grade. The mason is well underway with load bearing masonry walls. The steel erection for the two-story classroom wing is progressing. The electrical and plumbing contractors are also on site completing in wall rough-ins. The site contractor continues work on underground storm water lines and inlets. The front staff parking lot has the asphalt binder course installed and is being used for construction laydown as needed. The team has received a preliminary design to review for the required signal at the school entrance. This new 45-classroom school will be located next to the existing Mint Hill Middle School.

UPDATED
September 2021
Construction Manager /
General Contractor
Metcon (CM)
Architect
FWA
Location
11615 Idlewild Road Matthews, NC 28105
Overall Budget
$30,455,951
Project Manager
Chip Lofton
Construction Percent Complete
14%
Occupy On
August 2022
Board District
District 6

CURRENT PROJECT PHOTOS


LIVE CAMERA

Click here to open Live Cameraenter image description here in new tab.

ClickHere for 11.19.2020 Community Information Meeting

New ES Bain, Lebanon, Piney Grove

PREVIOUS CONSTRUCTION PHOTOS