K-8 Phase 2 - New gymnasium and specialty classrooms.
PROGRESS
The Mountain Island Lake Academy Gym/Classroom Addition construction manager continued with load bearing masonry and prepared for steel in the classroom areas. The site work contractor continued with final grading and preparing the crane pad for steel erection the beginning of January.