Mountain Island Lake Academy

SCOPE OF WORK
K-8 Phase 2 - New gymnasium and specialty classrooms.

PROGRESS
The Mountain Island Lake Academy Gym/Classroom Addition construction manager is continuing with interior finishes. This includes the installation of the wood gym floor, final painting and acoustical panels. Due to the delay of the roof top HVAC unit a temporary unit has been installed to maintain conditioned space. The construction manager continues to focus on the exterior with final asphalt preparations, canopy installations and final grading.

UPDATED
April 2023
Construction Manager /
General Contractor
Whiting-Turner (CM)
Architect
ADW Architects
Location
7905 Pleasant Grove Road Charlotte, NC 28216
Overall Budget
$13,239,686
Project Manager
Kenneth Brown
Construction Percent Complete
74%
Occupy On
August 2023
Board District
District 1

CURRENT PROJECT PHOTOS