Mountain Island Lake Academy

SCOPE OF WORK
K-8 Phase 2 - New gymnasium and specialty classrooms.

PROGRESS
The Mountain Island Lake Academy project has progressed into the design development phase. This project consists of a building addition containing a middle school gymnasium, visual and performing arts classrooms. To address long lead time concerns the development of an early steel and roof procurement package are in progress. This project is scheduled to start in the spring of 2022 and is scheduled for completion in August 2023.

UPDATED
September 2021
Construction Manager /
General Contractor
Whiting-Turner (CM)
Architect
ADW Architects
Location
7905 Pleasant Grove Road Charlotte, NC 28216
Overall Budget
$10,488,400
Project Manager
Tim Ames
Construction Percent Complete
0%
Occupy On
August 2023
Board District
District 1

CURRENT PROJECT PHOTOS

no images were found



PREVIOUS CONSTRUCTION PHOTOS