Mountain Island Lake Academy

SCOPE OF WORK
K-8 Phase 2 - New gymnasium and specialty classrooms.

PROGRESS
The Mountain Island Lake Academy Gym/Classroom Addition construction manager completed the removal and replacement of unsuitable soils within the building pad has started installing the footings for the new building. The temporary staff/visitors lot binder base was installed along with temporary striping to establish the parking and queuing line. The landscaper completed the installation of the play field irrigation to allow the sod installations to begin.

UPDATED
August 2022
Construction Manager /
General Contractor
Whiting-Turner (CM)
Architect
ADW Architects
Location
7905 Pleasant Grove Road Charlotte, NC 28216
Overall Budget
$13,239,686
Project Manager
Kenneth Brown
Construction Percent Complete
10%
Occupy On
August 2023
Board District
District 1

CURRENT PROJECT PHOTOS