Montclaire Elementary School

SCOPE OF WORK
New 45-classroom replacement facility replacing school built in 1958.

PROGRESS
The construction manager for the Montclaire Elementary School (17) continued with final closeout of the new building. The salvage operations of the old school were completed and abatement began. Selective demolition of the old school began in areas were the abatement was completed. Structure demolition is schedule to begin mid-October. The new 45-classroom elementary school building has been occupied by the Principal and staff and is available for students as scheduled. Demolition and remaining site work will be completed in spring of 2021.

UPDATED
September 2020
General Contractor
Messer Construction (CM)
Architect
WHN
Location
5801 Farmbrook Drive Charlotte, NC 28210
Overall Budget
$28,559,390
Project Manager
Kenneth Brown
Construction Percent Complete
82%
Occupy On
August 2020
Board District
District 5

CURRENT PROJECT PHOTOS



PREVIOUS CONSTRUCTION UPDATES