Lincoln Heights Elementary School

SCOPE OF WORK
Repurpose and reopen as magnet school.

PROGRESS
Shamrock Gardens will be utilizing the Lincoln Heights Elementary building as swing space August 2020 - August 2022. Playgrounds were replaced and new digital signage was installed summer 2020. Based on Board approval in May 2021 the occupancy date has been moved to 2023.

UPDATED
June 2021
Construction Manager /
General Contractor
Architect
Neighboring Concepts
Location
1900 Newcastle Street Charlotte, NC 28216
Overall Budget
$4,588,675
Project Manager
Chip Lofton
Construction Percent Complete
0%
Occupy On
August 2023
Board District
District 2