Lansdowne Elementary School

SCOPE OF WORK
New 45-classroom school; replaces old school built in 1959 and relieve crowding at Elizabeth Lane ES.

PROGRESS
The Lansdowne Elementary School construction manager's trade contractors are completing the remaining punch list items in the new building after school hours. The old facility is now removed and final site grading for playfield installation is ongoing. New playgrounds are scheduled for installation in late February. The demolition and remaining site work will be completed in early 2023.

UPDATED
December 2022
Construction Manager /
General Contractor
Edifice (CM)
Architect
Perkins Eastman
Location
7200 Folger Drive (New) Charlotte, NC 28270
Overall Budget
$33,804,188
Project Manager
Chip Lofton
Construction Percent Complete
95%
Occupy On
August 2022
Board District
District 5

CURRENT PROJECT PHOTOS


PREVIOUS CONSTRUCTION PHOTOS