New K-8 Language Immersion facility located on the old J.M. Alexander Middle School site.
PROGRESS
The New K-8 Language Immersion North (17) construction manager continued installing finishes. The final paint and hard tile in the classroom wing bathrooms is being completed and bathroom fixtures are being installed. The wood doors and casework are also being installed at the classrooms. The electrical contractor is installing the light fixtures. The wood gym floor is down and bleachers are being installed. The temporary storm water pond is being converted to the sand filter for permanent use. The Hambright Road improvements have been scheduled with local underground utility contractors to relocate existing lines as needed.