J.T. Williams Montessori

SCOPE OF WORK
Project includes building renovations to J.T. Williams Montessori magnet.

PROGRESS
The construction manager for JT Williams Secondary Montessori completed interior renovations for the 100 Building with the exception of the mechanical roof top units that have been impacted by supply chain issues. This, in conjunction with the timing of the required fire-line water taps, will impact the 100 Building occupancy in early spring. The 200 Building renovations continue as selective demolition is complete. The mechanical, electrical and plumbing subcontractors are working on above ceiling rough-ins. Site work including new fire line tie in is scheduled for summer 2023.

UPDATED
April 2023
Construction Manager /
General Contractor
New Atlantic (CM)
Architect
FWA
Location
2400 Carmine St Charlotte, NC 28206
Overall Budget
$17,032,600
Project Manager
Chip Lofton
Construction Percent Complete
68%
Occupy On
August 2024
Board District

CURRENT PROJECT PHOTOS



PREVIOUS CONSTRUCTION PHOTOS