Project includes the design and construction for renovations of 300 building and a new 16 classroom building.
PROGRESS
The construction manager for the Garinger Addition and Renovation project proper has completed commissioning activities for the 300 building renovations. The replacement glass and glazing components have been received. The contractor is currently fabricating the window systems and is currently scheduled to begin the installation of the replacement systems over summer break.