Project includes the design and construction for renovations of 300 building and a new 16 classroom building.
PROGRESS
The Garinger Addition and Renovation construction manager continued with interior and exterior activities. Exterior metal panels continued with plans to complete the first week of May. Exterior site work progressed with sidewalks, curb and gutter, detention pond conversion along with prepping for landscaping. Ceiling tile was installed throughout the addition along with installation of ceiling devices; security, cameras, speakers, etc. VCT flooring continued in available areas. In addition the renovation work in the 300 building is being coordinated and will commence this summer.