Garinger High School

SCOPE OF WORK
Project includes the design and construction for renovations of 300 building and a new 16 classroom building.

PROGRESS
The Garinger Addition and Renovation construction manager completed the under slab electrical and plumbing rough-ins and has poured the slab on grade. They continued with low voltage conduit trenches to the existing buildings that will provide the connectivity. The addition is scheduled to be occupied August of 2022 and the renovation to be occupied in January of 2023.

UPDATED
September 2021
Construction Manager /
General Contractor
Balfour Beatty (CM)
Architect
LS3P
Location
1100 Eastway Drive Charlotte, NC 28205
Overall Budget
$5,986,979
Project Manager
Ken Brown
Construction Percent Complete
10%
Occupy On
January 2023
Board District
District 3