Garinger High School

SCOPE OF WORK
Project includes the design and construction for renovations of 300 building and a new 16 classroom building.

PROGRESS
The Garinger Addition and Renovation construction manager progressed well in the month of August. The school occupied the CTE building and completed preparations for use. FF&E removed the remaining school content from the 300 Building allowing the selective demolition to continue. The MEP trades began the above ceiling installations and the plumber began installations below grade.

UPDATED
August 2022
Construction Manager /
General Contractor
Balfour Beatty (CM)
Architect
LS3P
Location
1100 Eastway Drive Charlotte, NC 28205
Overall Budget
$5,986,979
Project Manager
Ken Brown
Construction Percent Complete
73%
Occupy On
January 2023