Garinger High School

SCOPE OF WORK
Project includes the design and construction for renovations of 300 building and a new 16 classroom building.

PROGRESS
The construction manager for the Garinger Addition and Renovation project completed final cleaning of the 300 building classrooms with the corridors to follow in January. The fire and domestic water taps were completed late December. The fire pump is schedule to start the beginning of January for final sign off from the Fire Marshall.

UPDATED
December 2022
Construction Manager /
General Contractor
Balfour Beatty (CM)
Architect
LS3P
Location
1100 Eastway Drive Charlotte, NC 28205
Overall Budget
$5,236,979
Project Manager
Ken Brown
Construction Percent Complete
97%
Occupy On
January 2023
Board District
District 3

CURRENT PROJECT PHOTOS