East Mecklenburg High School

SCOPE OF WORK
This project will provide for the design, and construction of a new 30 classroom building.

PROGRESS
The construction manager for East Mecklenburg High School is working towards substantial completion. The above ceiling inspections have been completed and ceiling tile is being installed. The floor finishes are also being finalized with VCT wax to follow. The exterior hardscapes are being tied into existing walks and pavement for completion. The team anticipates starting FF&E installation in early May.

UPDATED
April 2022
Construction Manager /
General Contractor
Turner (CM)
Architect
Morris Berg
Location
6800 Monroe Road Charlotte, NC 28212
Overall Budget
$10,405,411
Project Manager
Chip Lofton
Construction Percent Complete
90%
Occupy On
August 2022
Board District
District 4

CURRENT PROJECT PHOTOS