East Mecklenburg High School

SCOPE OF WORK
This project will provide for the design, and construction of a new 30 classroom building.

PROGRESS
The construction manager for East Mecklenburg High School has started pouring the slab on grade as footing and foundation walls are complete. The underground infrastructure to support the new building is also being coordinated with the public utilities. The existing primary power line feeding the 500 Building is scheduled to be relocated as part of the project but delays with Duke Energy have impacted the schedule. The next phase of the project will not be able to start until the line is relocated. The project team is working through supply chain logistics and issues with material availability. In some cases, product substitutions are being considered to maintain overall construction schedule.

UPDATED
June 2021
Construction Manager /
General Contractor
Turner (CM)
Architect
Morris Berg
Location
6800 Monroe Road Charlotte, NC 28212
Overall Budget
$15,058,594
Project Manager
Chip Lofton
Construction Percent Complete
15%
Occupy On
August 2022
Board District
District 4