Collinswood Language Academy

SCOPE OF WORK
New 63-classroom K-8 facility on the site of the Smith Family Center.

PROGRESS
The Collinswood Language Academy (17) project team continued working through the final completion phase of the project. The focus was on finalizing commissioning items and financial reconciliation. The FF&E activities were completed and the staff occupied the facility in late June.

UPDATED
June 2020
Construction Manager /
General Contractor
Turner Construction (CM)
Architect
Perkins Eastman
Location
5621 Flagstaff Drive Charlotte, NC 28210
Overall Budget
$42,272,540
Project Manager
Kenneth Brown
Occupy On
August 2020
Board District
District 5