Career and Technical Education

SCOPE OF WORK
Phase I CTE upgrades at Olympic, Harding, Garinger and South Mecklenburg.

PROGRESS
The CTE projects at Harding and South Mecklenburg continue to progress. The load bearing structural walls are complete and temporary shoring is being removed. The interior walls are framed and in wall rough-ins are complete and the drywall is complete at South Mecklenburg. The Harding project consists of renovations to existing classrooms in the auditorium building to develop a suite of technology classrooms. The project at South Mecklenburg consists of renovating the old kitchen area into a culinary arts lab and classroom. Harding and South Mecklenburg are scheduled for completion in January 2022.

UPDATED
September 2021
Construction Manager /
General Contractor
Architect
Location
Overall Budget
$10,159,765
Project Manager
Chip Lofton
Construction Percent Complete
45%
Occupy On
January 2023
Board District

CURRENT PROJECT PHOTOS

no images were found



PREVIOUS CONSTRUCTION PHOTOS