Briarwood Elementary School

SCOPE OF WORK
45-classroom replacement facility; replaces school built in 1956.

PROGRESS
The construction manager for the Briarwood Elementary replacement school (17) continued the installation of storm pipe, domestic water, gas and fire lines. The main drive curb, gutter and stone base was installed. The underground rough-in continued in the classroom building for building slabs to be poured in the classroom wing. The mason maintained the schedule durations installing the load bearing masonry in the cafeteria/multipurpose rooms.

UPDATED
September 2020
Construction Manager /
General Contractor
New Atlantic
Architect
ADW
Location
1001 Wilann Drive Charlotte, NC 28215
Overall Budget
$31,962,730
Project Manager
Ken Brown
Construction Percent Complete
17%
Occupy On
August 2021
Board District
District 4

CURRENT PROJECT PHOTOS



PREVIOUS CONSTRUCTION PHOTOS