Billingsville Montessori Upfit

SCOPE OF WORK
Repurpose Billingsville for relocated Montessori PK-6 program; demolish Chantilly. Cotswold to occupy Billingsville August 2025; Chantilly Montessori to occupy Billingsville 2027.

PROGRESS
Summer construction phase includes mechanical controls upgrades and staff/visitor parking paving. The mechanical contractor has completed their scope allowing testing and balancing to proceed. The paving of the staff/visitor parking lot is complete.

UPDATED
July 2026
Construction Manager /
General Contractor
Clancy & Theys in Partnership with The Daniele Company
Architect
WHN
Location
124 Skyland Avenue Charlotte, NC 28205
Project Manager
Chip Lofton
Construction Percent Complete
85%
Occupy On
August 2027
Board District
District 4